Horizontal Directional Drilling
Berri LTA-43 / Abu Ali Project
A 30″ carbon steel pipeline installed by HDD over 900 m, and a 40″ steel casing with 30″ product pipeline micro-tunnelled over 450 LM.
30″
HDD · Pipe
900 m
HDD · Length
40″ · 30″
Micro-Tunnelling · Pipe
450 m
Micro-Tunnelling · Length
Scope of Work
- HDD of 30″ carbon steel (CS) pipeline — 900 m
- Micro-tunnelling installation of 40″ steel casing and 30″ product pipeline — 450 LM
Where the work was
- Site
- Abu Ali Island, Jubail, Saudi Arabia
- Total installed
- 1,350 m
The pin marks the field or corridor, not the exact crossing — the precise alignment is commercially sensitive.